Manufacturing processes, the MSPRO Wear Material Systems, inspection support and project documentation. Written to be read alongside a drawing or a procedure.
Section 01
Manufacturing & processes
Process selection follows the wear mechanism, component geometry, substrate and functional requirements. Process availability and component suitability are confirmed during technical review.
Five surface engineering routes.





Section 02
MSPRO Wear Material Systems
MWMS is the commercial designation for MSPRO Wear Material Systems. The material is selected to suit wear, impact, temperature and component requirements.
| Material code | Material system |
|---|---|
| MWMS-55 | Chromium Carbide Overlay |
| MWMS-60 | Chromium Carbide Overlay |
| MWMS-65 | Chromium Carbide Overlay |
| MWMS-80 | High-Alloy Chromium Carbide Overlay |
| MWMS-H | Overlay for Elevated-Temperature Service |
| MWMS-TC06000 | Tungsten-Bearing Overlay |
| MWMS-CF60 | Smooth Overlay Series |
| MWMS-CF80 | Smooth Overlay Series |
| MWMS-WC40P | Tungsten Carbide Cladding System |
| MWMS-WC70P | Tungsten Carbide Cladding System |
| MWMS-3401 | Special Alloy Wear Material |
MWMS codes identify materials, not guaranteed hardness levels.
MWMS codes are a separate material identification system from the HI, HA and HX hardfacing welding consumables. They are not interchangeable references.
Section 03
Inspection & analysis support
Inspection scope and documentation are agreed before supply, according to the component, the material system and the information the customer requires.
Dimensional and visual
- Dimensional inspection against the agreed drawing
- Visual condition of the overlay and the component surface
- Thickness, geometry and fixing details where applicable
Hardness and composition
- Hardness testing where the material system and project require it
- Chemical composition analysis where agreed
Metallography and trials
- Metallographic examination where agreed
- Selected wear or process trials where available
Records
- Inspection points recorded against the agreed plan
- Document requirements agreed before supply
Section 04
Project quality & documentation
- Incoming material checks
- Material is checked against the specification before it enters the process.
- Process inspection
- Applicable process inspection points are carried out during manufacture.
- Final inspection
- Finished components are inspected against the agreed requirements before packing.
- Packaging
- Packing requirements are agreed per project, including protection for the overlay surface.
- WPS
- Welding procedure specifications are prepared where the project requires them.
- ITP
- Inspection and test plans are agreed with the customer for the project scope.
- Technical records
- Supporting technical records are supplied as agreed for the project.
Documentation is agreed per project. No certifications or testing capabilities beyond those agreed for a specific project are implied.
Technical note
Technical information is provided as a general guide. Confirm base material, joint design, welding procedure, shielding gas and the applicable technical data sheet before use.
Discuss a material system or a project specification.
Send the drawing, the duty and the inspection requirements you need documented, and we will confirm what can be supplied.